Attach the videography with the qualification report.Carry out the videography for the same test.Airflow pattern study shall be done as per the current version of SOP provided by the approved external agency.AIRFLOW PATTERN TEST – HVAC QUALIFICATION :.Pressure differentials shall meet the requirement as specified in system specification along with room specifications included in specific HVAC.Differential pressure of the room shall be recorded once in two hours and it shall be continued for 72 hours.Observe the differential pressure through the Magnehelic gauge.To avoid unexpected changes in air pressure and to establish a baseline, respective control like all doors in the facility must be closed and no personal movement shall be allowed during the test.The air handling system and respective dust collection system shall be in operation during this study.AIR PRESSURE DIFFERENTIAL TEST – HVAC QUALIFICATION :.During scanning percentage of the PAO penetration shown by the photometer shall be less than 0.01% through the filter media and shall be ‘zero’ through mounting joints.Observe and record the data given by the external agency in the respective qualification report.The integrity of the HEPA filter shall be performed as per the current version of SOP provided by an approved external agency.PAO, Smoke generator, Aerosol photometer, duly calibrated with National /international traceability certificate.
General Procedure for HVAC Qualification:.Maintaining data of HVAC qualification/requalification activity & to conclude the activity.
HVAC ANEMOMETER VERIFICATION
Verification of HVAC qualification/validation activities as per schedule and monitoring compliance with SOP.Quality Assurance Head shall be responsible for:.Reviewing and checking the HVAC qualification/requalification work is followed as per the standard operating procedure.Organization & coordination with external party for HVAC qualification / Requalification activities.Implementation and monitoring compliance of SOP.To attach the SOP provided by an external agency with this SOP as reference.Engineering head shall be responsible for :.Recording, checking the reading for correctness, and compilation of data in the report.Monitoring of qualification activities as per compliance with SOP.Quality Assurance shall be responsible for:.